Tongyu CSP project completes steam-pipe blowing in October 2026

The November 20, 2026 account recalls steam-pipe blowing from October 23 to 25: 47 hours and 66 blows. It describes a pre-operation commissioning milestone, with integrated system commissioning, unit startup and grid-connected generation still subsequent steps.

Recently, the Tongyu CSP project, for which the company is the EPC contractor, reached an important commissioning milestone as steam-pipe blowing was successfully completed, laying a solid foundation for subsequent integrated system commissioning and unit startup.

The steam-pipe blowing formally started at 20:00 on October 23, 2026 and ended at 19:00 on October 25, 2026, lasting 47 hours and completing a cumulative total of 66 blows.

As a key process before a CSP station enters operation, steam-pipe blowing uses high-temperature, high-pressure steam to flush the inner walls of the main-steam and reheat-steam pipes, thoroughly removing welding slag, oxide scale and other impurities left from manufacturing and installation, and preventing high-speed impurity-laden steam from damaging core components such as turbine blades and valves.

Before the blowing operation, the project team made full use of its EPC coordination and management strengths. Taking account of the CSP station's coupling of multiple heat sources and complex pipe routing, it specifically refined the dedicated steam-blowing plan, defined the core blowing scope, including steam guide pipes, main-steam lines and high-pressure bypasses, and appropriately matched blowing pressure, temperature and duration. By optimising temporary-system configuration and installing standardised inspection devices at the target-plate positions, it balanced blowing efficiency with inspection accuracy.

During blowing, the project team established a closed-loop control mechanism covering the entire process, coordinated all participating organisations, and arranged round-the-clock on-site staffing by operations, technical, safety and commissioning personnel. They monitored changes in key parameters, including wall temperature, differential pressure and flow rate, in real time, and recorded the sections, counts, parameters and target-plate inspection results for every blow. When pressure fluctuations and poor drainage occurred early in the blowing process, they immediately worked with equipment manufacturers and construction contractors to assess the issues and quickly adjust the combustion curve and drain-valve openings. The entire blowing process was safe and stable, with no safety incidents such as excessive temperature or pressure or pipe leakage. The final target-plate inspection results fully met requirements, successfully achieving the steam-blowing acceptance criteria.

Successful completion of the steam-pipe blowing task lays a solid foundation for subsequent full-unit startup and grid-connected generation. Next, the company's Tongyu CSP project team will continue to strengthen its EPC management responsibilities, closely follow milestone targets, steadily advance subsequent commissioning, strictly uphold safety and quality requirements, coordinate all participating parties in overcoming difficulties, and make every effort to ensure orderly project construction and achieve the production-start target as soon as possible.