Xinhua Huahui No. 1 CSP plant clears startup-readiness review before grid connection
The November 20, 2026 account reports the November 18 startup-acceptance committee's approval for whole-unit trial operation. It confirms readiness for reverse energisation and complete-unit startup and grid connection, not completed grid connection or commercial operation.
On November 18, the startup-acceptance committee meeting for Xinhua Huahui No. 1 CSP Plant was successfully held in the plant's front area. Sun Dayong, a member of the company's Party Committee and Deputy General Manager, chaired the meeting.
During the meeting, the committee members and relevant experts heard a report on the project's overall construction progress and unanimously approved the Resolution of the Startup-Acceptance Committee Meeting. They confirmed that the plant was ready for reverse energisation and complete-unit startup and grid connection, and agreed that the generating unit could begin whole-unit trial operation.
The successful holding of this startup-acceptance committee meeting marks the plant's fulfilment of all conditions for complete-unit startup and trial operation, sounding the call for an all-out final push towards grid connection.
All parties participating in the construction of Xinhua Huahui No. 1 CSP Plant are firmly implementing their primary responsibilities for production safety, carrying out detailed on-site risk classification and control and the investigation and rectification of hidden hazards, and keeping a close watch on equipment-defect rectification and the remaining commissioning tasks. They are strengthening coordination among the parties, concentrating resources on overcoming technical difficulties, and strictly safeguarding construction quality, making every effort to ensure the unit's smooth and stable grid connection.