October 2026: SDIC starts Dongwucha’s 100 MW fishery–PV second phase
The October 28, 2026 account records the first foundation pile on October 27 in Putian, Fujian. The second phase is under construction with supporting storage; its projected generation is separate from the first phase's full-capacity grid connection in May 2025.
On October 27, at the construction site in Dongwucha Village, Shanting Town, Putian, Fujian Province, a piling rig slowly drove in the first foundation pile, marking the official start of construction of SDIC Power's 100 MW fishery–PV power-plant project for Phase II of Dongwucha Area A in the Beian Economic Development Zone. Above the rippling tidal flats, a new ‘blue field’ has begun to grow.
Project background
At the new starting point of the 15th Five-Year Plan, SDIC Power is firmly implementing the concept of green development, closely following the country's requirement to actively and prudently advance carbon peaking and carbon neutrality, and continuing to strengthen and improve its clean-energy business, with renewable energy as the mainstay. This project is an important move in the company's coastal renewable-energy layout. The project's first-phase 100 MW PV power plant achieved full-capacity grid connection in May 2025 and delivers an average of approximately 150 million kWh of clean electricity annually.
The second phase will use space reserved at the first-phase step-up substation to expand the main transformer, distribution building and supporting energy-storage facilities, optimising and upgrading the grid-connection system. Its electricity will be collected together with that of the first phase and use a shared export route, achieving intensive and efficient use of resources.
The second phase has a registered installed capacity of 100 MW and will be equipped with a supporting energy-storage system, continuing the environmentally friendly ‘fishery–PV’ development model. More than 180,000 high-efficiency PV modules will be installed above the ponds, generating electricity from sunlight above the panels while aquaculture takes place below. The PV panels will provide shade, suppress algae and regulate water temperature, creating a suitable growth environment for aquatic products and achieving ‘two uses for one pond, fishery and PV coexisting, and two harvests from one expanse of water’.
Project outlook
The project was included in Fujian Province's 2024 PV Power Plant Development and Construction Plan. All preliminary studies, specialised assessments and approval procedures have been completed, and the conditions for starting construction are in place. The site has favourable sunlight conditions, with annual total solar irradiation exceeding 5,300 MJ/m², placing it in an area rich in solar resources.
The project team is committed to high-standard planning and meticulous control, focusing on key technical aspects such as pile depth and corrosion protection and scientifically optimising the construction plan. It will work to create a high-quality project capable of withstanding the long-term tests of sea winds and tides.
Project significance
After completion and entry into operation, the second-phase project will be able to provide an average of approximately 150 million kWh of clean electricity annually. The first and second phases together will have a total installed capacity of 200 MW and deliver nearly 300 million kWh of green electricity each year, growing into a highly representative fishery–PV green-energy base on the Fujian coast.
In terms of ecological benefits, the project will be able to save tens of thousands of tonnes of standard coal annually and reduce carbon dioxide emissions by more than 100,000 tonnes, while also cutting sulphur dioxide and nitrogen oxide emissions. Its ecological and carbon-reduction benefits will continue throughout a 25-year operating period, building substantial green momentum for the local energy transition and helping realise the goals of carbon peaking and carbon neutrality.
From the successful grid connection of the first phase to the start of construction of the second, SDIC Power is deepening its presence along the Meizhou Bay coast. Drawing on the area's tidal-flat resources, it is turning sunlight into clean electricity and ecological strengths into development strengths, while empowering local prosperity and higher incomes as it develops the renewable-energy industry. Through practical action, it continues to write a new chapter of seaward development and progress towards a greener future.