Dunhuang Guosheng Nandu’s 200 MW/800 MWh storage project connects to grid and begins trial operation
The November 19, 2026 account reports grid connection and entry into a 24-hour trial-operation stage on November 14. The project uses liquid-cooled LFP storage and a new 330 kV substation; trial operation is not described as completed commercial-operation acceptance.
On November 14, the Dunhuang Guosheng Nandu 200 MW/800 MWh independent energy-storage demonstration project, built under an EPC contract by Energy China's Gansu Institute, was successfully connected to the grid and put into operation, entering a 24-hour trial-operation stage. All equipment at the station was operating normally.
Located in the Dunhuang Optoelectronic Industrial Park, the project is Dunhuang's first grid-side independent energy-storage demonstration project. It includes a newly built 330 kV step-up substation connected to the 330 kV Xingguang substation. The storage system uses prefabricated-container lithium iron phosphate liquid-cooled energy storage, comprising 40 sets of 5 MW integrated step-up containers and 160 sets of 5 MWh storage-battery containers. Since construction started on November 5, 2025, the EPC project team has overcome multiple pressures, including tight supply lead times for core equipment and lengthy external coordination chains, coordinated design, procurement, construction and commissioning, strictly implemented safety and quality controls, closely managed the entire grid-connection and commissioning process, worked backwards from deadlines, established daily tracking and weekly coordination mechanisms, and worked all out towards the grid-connection milestone.
After entering operation, the project will fully perform peak-shaving and valley-filling, frequency and voltage regulation, and emergency grid-support functions. It will effectively smooth fluctuations in renewable-energy output, address the regional grid's peak-regulation shortfall, greatly improve renewable-energy consumption in the Dunhuang area, enhance operational flexibility and power-supply reliability, and provide strong support for construction of the Hexi clean-energy base, transformation of the regional energy mix and implementation of the ‘dual-carbon’ goals.
Next, the project team will continue to address outstanding works and defects, project payments and engineering handover, provide post-commissioning follow-up support, and successfully fulfil its obligations throughout the project cycle.