Alxa-Wuhai 2 GW wind-PV-storage project achieves first grid connection
The November 16, 2026 report records successful back-energisation of stations 1, 2 and 3 and first grid connection on November 12. The project comprises 300 MW of wind, 1,700 MW of PV and 300 MW/600 MWh of storage; full-capacity wind-solar-storage grid connection remains a year-end goal.
On November 12, Inner Mongolia's first cross-league/city cooperative new-energy project designed to provide a guaranteed power supply—the 2 million kW ‘Alxa Power to Wuhai’ regional mutual-support new-energy project—successfully completed back-energisation across all stations (Nos. 1, 2 and 3) and its first grid connection on the first attempt, laying a solid foundation for full-capacity grid connection of the project's wind, solar and storage facilities by the end of the year.

The project reportedly involves total investment of approximately RMB 7.924 billion. Its construction scope comprises 300,000 kW of wind power and 1.7 million kW of PV, with supporting energy-storage facilities of 300,000 kW/600,000 kWh installed at the same time. Storage will provide peak shaving and valley filling, smoothing fluctuations in wind and solar generation and ensuring that exported power is safe, stable, reliable and controllable.
Pang Yu, a member of the general Party branch committee and deputy manager of the Mengxi Centre of Inner Mongolia Mengneng New Energy Co., Ltd., explained: ‘“Alxa Power to Wuhai” is the autonomous region's first cross-league/city new-energy project designed to provide a guaranteed power supply. Through medium- and long-term green-electricity agreements, it can steadily transmit 4.18 billion kWh of clean electricity to Wuhai each year.’
According to the information provided, the project innovatively adopts a model of ‘power generation above the panels, planting below the panels, and sand control and soil improvement’, supplying green electricity while restoring desertified land. Once operational, it can rehabilitate and restore 87,000 mu of desert, save more than 1.26 million tonnes of standard coal annually and reduce carbon dioxide emissions by more than 3.8 million tonnes, turning the desert into a power-generation site and a sand-control site. After commissioning, the project will continue to optimise the energy-supply structures of Alxa and Wuhai, open two-way channels for local new-energy use and cross-regional transmission, improve regional renewable-energy accommodation, and support the green transformation of energy-intensive industries. It will provide solid, reliable green-electricity support for industrial restructuring, green and low-carbon economic and social transformation, and steady implementation of the ‘dual carbon’ goals in both areas.