Gangcha’s 200 MW grazing–PV first phase reaches full-capacity grid connection
The November 18, 2026 account records full-capacity grid connection at 11:26 on November 17 for the 200 MW first phase of a planned 1 GW project. This phase includes 30 MW/60 MWh of storage and a 330 kV substation; annual generation and emissions figures are estimates.
At 11:26 on November 17, the Haibei Huisheng Cuowenbu solar-plus-storage plant successfully completed its grid-connection operation, with all equipment parameters operating stably. This marked the formal start of electricity-generation operations and full-capacity grid-connected generation for the 200 MW first phase of the 1 GW complementary grazing–PV project. It is a key achievement in Gangcha County's implementation of the ‘dual carbon’ strategy and provincial and prefectural arrangements for clean-energy industry development, marking a solid step forward in countywide large-scale new-energy development and integrated utilisation and injecting new green momentum into green, low-carbon, high-quality development of the county economy.
Facing multiple challenges including high altitude, complex climatic conditions, a short effective construction season and high construction standards, Gangcha County resolutely implemented the Haibei prefectural Party committee and government's ‘100-day intensive effort’ work arrangements. It proactively supported Haibei Huisheng New Energy Co., Ltd., scientifically coordinated construction schedules, continuously optimised construction organisation and seized the limited construction window. By working backwards from deadlines, using chart-based task management and advancing closely sequenced work, it orderly completed construction tasks including PV module installation, equipment installation and commissioning, storage-system integration, step-up substation facilities and export-line erection.
This phase comprises 200 MW, together with a 30 MW/60 MWh storage system and a 330 kV step-up substation. Following successful grid connection, the county's total completed, grid-connected new-energy installed capacity increased from 1,380.5 MW to 1,580.5 MW, further expanding clean-energy development and strengthening support for the county's new-energy industry. Based on Gangcha's grassland ecology, the project promotes coordinated development of PV generation and grassland livestock farming while safeguarding the grassland's original use and normal livestock production. It explores a new model integrating clean-energy development with ecological animal husbandry, laying a sound foundation for subsequent new-energy project development and construction.
According to estimates, after completion and commissioning the project can deliver average annual grid exports of 361.24 million kWh, saving approximately 206,800 tonnes of standard coal and reducing carbon dioxide emissions by approximately 515,200 tonnes each year. Alongside increasing clean-energy supply and improving the regional energy mix, it will further deliver energy-saving, emissions-reduction and ecological-protection benefits, contributing to the ‘dual carbon’ goals and the Qilian Mountains' ecological security barrier. At the same time, through village–enterprise cooperation and other means, the project helps Ningxia Village and Niannaisuoma Village in Quanji Township strengthen their collective economies, creates nearby employment for local herders, broadens income channels and ensures that clean-energy development benefits reach local communities more widely and effectively.
Next, Gangcha County will continue to build on its resources and actual industrial-development conditions, fully leverage its clean-energy resource advantages, steadily advance subsequent new-energy projects and actively explore new models integrating clean energy with ecological animal husbandry. It will continue to expand opportunities in green-electricity trading and energy consumption, extend the new-energy industrial chain and enhance its value chain, accelerate the conversion of resource advantages into industrial and development advantages, and make every effort to improve the quality and efficiency of the county's clean-energy industry, providing strong support for green, low-carbon, high-quality economic and social development.