Three Gorges Energy connects first 119 MW of Tiandong’s 150 MW agrivoltaic project

The Guangxi project reached first grid connection on November 7; its full-capacity annual generation is projected at 175 million kWh.

On November 7, the first 119 MW of Three Gorges Energy's 150 MW agrivoltaic project in Tiandong, Guangxi connected to the grid and began generating electricity, bringing new momentum to the green transition and rural revitalisation of the old revolutionary base area of Baise.

Photovoltaic arrays at the Tiandong agrivoltaic project site.
Photovoltaic arrays at the Tiandong agrivoltaic project site.

Located in Tiandong County, Baise, Guangxi, the project has an installed capacity of 150 MW on the AC side and a newly built 220 kV step-up substation. It uses fixed mounting structures and optimises the spacing of photovoltaic panels to ensure crops receive sufficient light. Dwarf grafted mango trees, pumpkins, medicinal plants and other crops are cultivated, creating a three-dimensional arrangement of ‘electricity generation on the panels and cultivation beneath them’.

Since construction began, the project team has upheld Party-building leadership, drawing on the Party branch's role as a strong organisational base and Party members' exemplary role to integrate Party-building with engineering construction. During construction, the project faced unfavourable conditions including dispersed work areas, complex terrain, numerous crossings along the power-export line and difficult coordination. The project-management team adjusted construction schedules scientifically, coordinated construction organisation and strengthened safety and quality management throughout the process to ensure efficient and orderly progress. On-site production and operations personnel remained on the front line, steadily carrying out equipment installation, commissioning, acceptance and testing, and strictly implementing grid-connection tasks, providing assurance for the successful connection of the first units and subsequent full-capacity commissioning.

Project personnel mark first grid connection at the Tiandong project.
Project personnel mark first grid connection at the Tiandong project.

Once the project is operating at full capacity, annual generation is expected to reach 175 million kWh, equivalent to saving approximately 52,000 tonnes of standard coal and reducing carbon dioxide emissions by approximately 142,000 tonnes. The project will create a new model for integrated clean-energy and modern-agriculture development in Tiandong County, providing a practical reference for developing agrivoltaic projects in similar areas with abundant agricultural resources.