Projects
Daofu Yari’s 50 MW/100 MWh grid-forming storage completes tests and 72-hour trial
A November 13, 2026 report says the storage system associated with the Yari ‘1+N’ project's 500 MW PV plant, package II, completed on-site grid tests and a 72-hour continuous trial. It is ready for commissioning; the report does not establish full commercial operation of the storage system or the PV plant.
In Daofu County, Garze Prefecture, Sichuan Province, the 50 MW/100 MWh grid-forming energy-storage project associated with the 500 MW photovoltaic power station of the Yari ‘1+N’ project (package II) has completed all on-site grid-related tests and passed a 72-hour continuous trial run, formally meeting the conditions for commissioning.

The project uses advanced grid-forming converter technology and has successfully verified the reliability of grid-forming storage in supporting a high proportion of renewable generation connected to the grid. It can effectively improve regional grid-support capabilities and power-export capacity, representing a successful exploration of a new model for connection to weak grids on the plateau.