Damao Banner’s 300 MW grassland-solar pilot reaches full grid connection, pairing PV generation with a 220 kV substation and 45 MW/90 MWh of battery storage.
On November 4, China's first desert-grassland "grassland-solar complementarity" pilot project, in its photovoltaic portion, and the first new-energy project owned by a Baotou municipal state-owned enterprise to connect to the grid and generate electricity, the 300,000 kW desert-grassland grassland-solar pilot in Damao Banner, achieved full-capacity grid connection and generation in Bayin Aobao Sumu, Damao Banner, Baotou. The milestone marks a distinctive development path for Damao Banner that closely integrates new-energy development with grassland ecological management.
The project was financed and built by Inner Mongolia Guoyun Mingsheng New Energy Co., Ltd., a subsidiary of Mengxi New Energy Group.

At 10 a.m., the project's grid-connection launch ceremony formally began. "I declare that the 300,000 kW desert-grassland grassland-solar pilot project in Damao Banner is connected to the grid! Start!" Following the instruction from Zhang Qiang, Party secretary and chairman of Mengxi New Energy Group, applause rang out and the atmosphere was enthusiastic. Representatives of the local government, state-owned energy enterprises, and the project's development and construction organisations gathered to witness this important historic moment in Damao Banner's green, low-carbon, high-quality development.
After the ceremony, the reporter visited the project's main control room and step-up substation. On the display screens, data on real-time generation, equipment operation and grid load changed dynamically and could be precisely controlled. Several staff members watched the screens closely, monitoring operating data in real time. Inside the step-up substation, two main transformers operated steadily, raising the voltage of the electricity generated by the photovoltaic panels before continuously sending it into the grid through the Kailinhe 500 kV substation.

In the main control room, Zhao Jiaxu, chairman of Inner Mongolia Guoyun Mingsheng New Energy Co., Ltd., told the reporter that, with strong support from the Baotou municipal Party committee and government and the Damao Banner Party committee and government, and under the careful guidance of Mengxi New Energy Group, construction formally began in August 2025. Faced with numerous challenges, including a short effective construction window on the grassland, complex weather conditions and demanding ecological-protection requirements, all those involved overcame difficulties, advanced the work efficiently and completed the entire construction programme on schedule and to the required quality. The project has total investment of RMB 1.05 billion and total installed capacity of 300 MW, with a supporting 220 kV step-up substation and a 45 MW/90 MWh energy-storage system, and feeds electricity into the Kailinhe 500 kV substation. After full commissioning, annual average generation can reach 480 million kWh and annual carbon dioxide emissions can be reduced by approximately 420,000 tonnes, delivering significant energy-saving, carbon-reduction and ecological benefits.

Unlike the single-purpose generation model of conventional photovoltaic projects, this project's principal innovative advantage is the mutually reinforcing, coordinated combination of new-energy development and grassland ecological restoration. To leave sufficient growing space for forage beneath the panels, the project raised the photovoltaic mounting structures to two metres. Drawing on the characteristics of Damao Banner's desert-grassland terrain, the project innovatively adopted an integrated construction model combining "degraded desert-grassland restoration, photovoltaic development and utilisation, and improved carbon sequestration", establishing a locally adapted grassland-solar technology system for northern desert grasslands. Six high-quality grass species that tolerate cold and drought and suit local growing conditions are planted beneath the panels. Through scientific planning and a "no-till overseeding" approach, grass seeds are sown directly into the soil without damaging its existing structure. Combined with appropriate supplementary planting and subsequent management, the project has implemented ecological management and restoration across 5,420 mu of degraded desert grassland, truly achieving clean generation above the panels and ecological restoration below, dual use of the land and mutual ecological benefits, revitalising degraded, unused grassland while delivering ecological, social and economic benefits.
The successful grid connection of China's first desert-grassland grassland-solar pilot project is a vivid example of Damao Banner building on its wind and solar resources, thoroughly implementing the dual-carbon strategy and strengthening the ecological-security barrier in northern China. The project has successfully explored a new path integrating "new energy + ecological management" in desert-grassland areas, accumulating valuable experience for integrated green development in similar areas across the autonomous region and the country, while also leaving real research data and practical examples.